Tuesday, December 6, 2016

Project Completed!!!!

Work Completed, November 21st to December 3rd 
·         Paved final surface layer of asphalt pavement along North Branch Road
·         Complete asphalt driveway restorations along North Branch Road
·         Installed and graded final layer of topsoil along North Branch Road
·         Completed sod installation along North Branch Road
·         Completed sod installation along Longvalley Road
·         Completed final testing of underground utilities along North Branch Road
·         Adjust manholes in parkways
·         Miscellaneous repairs to underground utility structures.

Work to be completed in Spring of 2017
·         Review all sod restorations to ensure a healthy stand of grass is established
·         Perform final walk-through of project with Village staff.
·         Minor repairs along the project site

With the arrival of the first snow event of the season, construction operations are completed. The weather did hold out long enough for all the major items to be completed, including sod installation which was completed the day prior to the snow arriving!!!

Please be assured, although the sod was installed at the end of the season, the Village will perform a site walk through in the Spring of 2017 to ensure a healthy stand of grass is established prior to final project close-out.

This will be the last Blog Post of the project. We hope that you found the information provided informative and useful. If you have any additional concerns or questions, please contact the Village Project Manager, Chris Gray, at 847-904-4325.

Thanks again for all your patience and understanding during this long construction season / project. We are hopeful you are satisfied with the results, now that the project is completed.

Friday, November 18, 2016

Paving to be Completed Prior to Thanksgiving!!!

Work Completed, November 4th to November 18th  
·         Rough grading of landscape restoration areas along Longvalley Road
·         Fine grading and topsoil installation along Longvalley Road
·         Sod installation along Longvalley Road
·         Paving of asphalt surface layer along Longvalley Road
·         Complete asphalt driveway restorations along Longvalley Road
·         General site clean-up along Longvalley Road
·         General site clean-up at construction staging area on east end of Longvalley Road
·         Roadway excavation and aggregate base course installation along North Branch Road
·         Paving first layer of asphalt pavement along North Branch Road
·         Installed first layer of asphalt driveway restorations along North Branch Road
·         Concrete driveway restorations along North Branch Road
·         Rough grading and topsoil installation along North Branch Road
·         Adjusting manholes to proper elevation.
·         Work in preparation for paving asphalt surface along North Branch Road
·         Nicor gas main and service replacements along Longvalley Road and North Branch Road is now completed.

Work Anticipated to be completed next week, prior to Thanksgiving Weekend
·         Install final layer and fine grading of topsoil along North Branch Road
·         Sod installation along North Branch Road
·         Perform final testing of underground utilities prior to asphalt paving of North Branch Road
·         Prepare for asphalt paving of surface layer along North Branch Road
·         Application of oil (tack coat) and sand on roadway prior to asphalt surface paving of North Branch Road
·         Pave surface layer of asphalt pavement on North Branch Road
·         Complete asphalt driveway restorations along North Branch Road 

Work to complete project after Thanksgiving Weekend
·         Complete sod restorations along North Branch Road
·         Minor repairs along the project site
·         Perform final walk-through of project with Village staff.

A letter has been delivered to those residents along Longvalley Road with brick paver driveways stating those driveways can be restored at this time. For those residents along North Branch Road, brick paver restoration can be scheduled following the asphalt surface paving scheduled for Tuesday, November 22nd.

Thanks again for all your patience and understanding throughout the construction process. A significant amount of work has been completed the past several weeks to get the project completed prior to the Thanksgiving Weekend / end of the construction season. 

Have a wonderful and enjoyable Thanksgiving!!!!

Monday, October 31, 2016

Longvalley Restoration On-Going. North Branch Storm Sewer Nearing Completion, Start Roadway Improvements.

Work Completed Last Week, October 24th to 29th  
·         Water service replacements along North Branch Road
·         Final water main connection at North Branch Road and Country Lane
·         Storm sewer installation along North Branch Road
·         Storm sewer replacement between 342 & 348 North Branch Road
·         Paved first layer of asphalt pavement along Longvalley Road from river to North Branch Road
·         Adjusting manholes to grade along Longvalley Road
·         Driveway replacements along Longvalley Road
·         Rough grading and topsoil installation in preparation for sod along Longvalley Road
·         Fine grading topsoil and sod installation along Longvalley Road
·         Nicor gas main and service replacements along Longvalley Road and North Branch Road is now completed.

Work Anticipated to be completed This week, October 31st to  November 4th
·         Complete storm sewer installation along North Branch Road
·         Begin roadway improvements including removing the existing roadway, grading, and installing new aggregate base course in preparation for asphalt pavement.
·         Continue with fine grading topsoil and sod installation along Longvalley Road

The restoration work along Longvalley Road is on-going and will be nearly completed by the end of next week. The contractor will leave approximately 2 feet of sod to be installed following the roadway surface paving. The reason for leaving this area along the edge of pavement is so the contractor can match the new asphalt surface once it is paved.

Storm sewer installation along North Branch Road is on-going and is expected to be completed by the end of the week. Once the storm sewer is completed, all underground utility work will be completed and the roadway improvements will begin.

As the weather gets colder, we are closing in on the end of the construction season. The long-range schedule to complete the project this year includes:

North Branch Road:
·         Week of November 7th – Complete roadway excavation and preparation work for asphalt pavement
·         Week of November 14th – Pave first layer of asphalt pavement. Begin driveway restorations.
·         Week of November 21st (Prior to Thanksgiving) – Adjust Manholes to grade. Pave surface layer of asphalt.
·         Week of November 28th – Sod Restoration. 

Longvalley Road
·         Week of November 7th – Clean site and demobilize from construction staging area
·         Week of November 14th – Pave final surface layer of asphalt pavement
·         Week of November 21st – Complete sod restoration.

Thanks again for all your patience and understanding throughout the construction process. A significant amount of work has been completed the past several weeks and will continue for the next several weeks to get the project completed prior to the end of the construction season. 

Saturday, October 15, 2016

Roadway Paving along Longvalley Road. Water Service Replacements along North Branch Road.

Work Completed Last Week, October 10th to 14th  
·         Water main installation along North Branch Road completed
·         Performed necessary testing and received required approvals to place new water main into service along North Branch Road
·         Replaced water services along North Branch Road from Country Lane to Central Parkway
·         Made connection between new water main and existing water main at intersection of North Branch Road and Central Parkway
·         Roadway excavation, grading, and base course installation along Longvalley Road
·         Installed storm sewer overflow at east end of Longvalley Road
·         Installed concrete curb & gutter on east end of Longvalley Road
·         Storm sewer installation started along North Branch Road
·         Nicor gas main and service replacements along Longvalley Road and North Branch Road nearly completed

Work Anticipated to be completed This week, October 17th to 21st  
·         Pave first layer of asphalt pavement along Longvalley Road from river to North Branch Road.
·         Water service replacements along North Branch Road from Longvalley Road to Country Lane

Water service replacements along North Branch Road will begin next week. Water services will be replaced from the new water main to the existing valve and box located in front of each home. During the water service replacement, water to individual homes will be shut-off for approximately 2-3 hours while the transition from the old service to the new service is made. The contractor will notify each resident individually regarding the approximate time and day of the water shut-off prior to turning off the water.

It is anticipated water service replacements along North Branch Road will take the majority of next week and may not be completed until early the week of October 24th. Once the water service replacement are completed, the contractor will continue with the storm sewer improvements along North Branch Road.

The contractor started the roadway improvements along Longvalley Road by removing the existing materials to the depth required for the new asphalt pavement along with grading and installing aggregate base course. It is anticipated the first layer of asphalt pavement will be installed next week. This will be a significant project milestone for those residents along Longvalley Road by providing a smooth driving surface and greatly reducing the amount of dust created.

Thanks again for all your patience and understanding.

Monday, October 3, 2016

Underground Utility Improvements Continue along North Branch Road

Work Completed Last Week, September 26th to 30th
·         Underground utility work along Longvalley Road completed.
·         Sanitary sewer service replacements on west side of North Branch Road completed
·         Sanitary sewer manhole replacements along North Branch Road completed
·         Water main installation started along North Branch Road
·         Storm sewer installation started along North Branch Road
·         Nicor Gas began gas main and service replacements along Longvalley Road

Work Anticipated to be completed This week, October 3rd to 7th  
·         Complete water main installation along North Branch Road
·         Continue with storm sewer installation along North Branch Road
·         Perform required testing on newly installed water main prior to placing into service and beginning water service replacements along North Branch Road
·         Nicor gas to continue with gas main and service replacements along Longvalley Road

The underground utility work along Longvalley Road is now completed; therefore, Nicor Gas re-mobilized to the site to begin the gas main and service replacements. It is anticipated Nicor will be completed with a majority of their work by the end of the week of October 3rd.  Once the gas main and service replacements are completed, Nicor will be contacting each resident individually to schedule a time to switch from the old gas service to the new gas service. Please coordinate with Nicor to allow for this transition to occur as quickly as possible.

The contractor has moved on to North Branch Road to begin underground utility improvements. The sanitary sewer improvements are mostly completed. The water main and storm sewer installation is on-going. It is anticipated water service replacements will begin later this week or next week.

Once water service replacements begin along North Branch Road, water services will be replaced from the new water main to the existing valve and box located in front of each home. During the water service replacement, water to individual homes will be shut-off for approximately 2-3 hours while the transition from the old service to the new service is made. The contractor will notify each resident individually regarding the approximate time and day of the water shut-off prior to turning off the water.

It is also anticipated the contractor will begin the roadway improvements along Longvalley Road the week of October 10th.

Thanks again for all your patience and understanding.

Monday, September 19, 2016

Underground Improvements on Longvalley Road Nearly Complete. Work on North Branch Road to Begin

Work Completed Last Week, September 12th to 16th   
·         Completed installation of mainline storm sewer along Longvalley Road
·         Continued with minor repairs of existing storm sewer along Longvalley Road
·         Replaced storm sewer services along Longvalley Road as needed or planned
·         Completed final water main connections along Longvalley Road
o   Water main improvements along Longvalley Road are completed.
·         Started abandonment of fire hydrants and valves on old water main system
·         Grinding-in-place of existing roadway along North Branch Road

Work Anticipated to be completed This week, September 19th to 23rd   
·         Complete minor repairs in existing storm sewer along Longvalley Road
·         Complete storm sewer service replacements along Longvalley Road as planned
·         Begin sanitary sewer service replacements on the west side of North Branch Road
·         Nicor Gas to begin gas main and service replacements along Longvalley Road from Country Lane east to river.

The contractor has continued to work on the storm sewer improvements and repairs to the existing storm sewer system along Longvalley Road. It is anticipated all underground utility improvements will be completed on Longvalley Road near the middle of this week.

The contractor will move to North Branch Road to begin underground utility improvements this week. The contractor will begin with replacing those sanitary sewer services on the west side of the street. The sanitary sewer services on the west side of the street go under the roadway; therefore, are being replaced as part of this project prior to the roadway improvements. The sanitary sewer services on the east side of the street will not be replaced as part of this project since they do not go under the roadway.

Nicor will also begin mobilizing back to the project site to begin gas main and service replacement along Longvalley Road from Country Lane to the river.

Thursday, September 8, 2016

Closure of Longvalley Road & Country Lane Extended to Friday, September 9th

Due to work not progressing as anticipated, the closure of the intersection at Longvalley Road and Country Lane will be extended through Friday, September 9th.

It is anticipated the work within the intersection will be completed by the end of the day on Friday.

Please use an alternate route around the intersection.

Thanks again for your patience.

Tuesday, September 6, 2016

Intersection of Longvalley Road and Country Lane Closed on Thursday, September 8th

In order to complete the storm sewer improvements within the intersection of Longvalley Road and Country Lane, the intersection will be closed to traffic in all directions on Thursday, September 8th from 7:00 AM to 5:00 PM.

The school districts and bus companies have been notified of this closure.

Please use an alternate route through the neighborhood and plan accordingly to avoid delays.

Storm Sewer Installation Continues along Longvalley Road

Work Completed Last Week, August 29th to September 2nd  
·         Continued with storm sewer installation along Longvalley Road.
·         Storm sewer main line completed from river to Rollwind Road
·         Site clean-up prior to Labor Day Weekend.

Work Anticipated to be completed This week, September 5th to 9th 
·         Continue with storm sewer installation along Longvalley Road from Rollwind Road west towards North Branch Road
·         Storm sewer installation within intersection of Longvalley Road and Country Lane.
·         Complete final water main connections at intersection of Longvalley Road and Rollwind Road

The contractor has continued with the storm sewer installation along Longvalley Road, working within several intersections last week and scheduled again for this week. Last week, work within the intersections of Crabtree Lane / Rio Vista Lane and Rollwind Road was completed.  This week, it is anticipated work will continue within the intersections of Rollwind Road and Country Lane.

Thank you for all your patience as getting through these intersections and around the neighborhood has been challenging. The Village of Glenview has been in contact with the school districts in the area to update them on the construction progress and schedule to ensure the buses are able to navigate through the construction area.

It is anticipated the storm sewer improvements along Longvalley Road will be completed within the next 2 weeks. Once the storm sewer is completed, the contractor will begin the underground utility improvements along North Branch Road.

Monday, August 29, 2016

Water Main Improvements Completed along Longvalley Road. Storm Sewer Improvements Begin

Work Completed Last Week, August 22nd to 26th 
·         Completed water service replacements along Longvalley Road between Country Lane and North Branch Road
·         Completed connections between the existing water main and the new water main at North Branch Road and Country Lane
·         Began storm sewer installation along Longvalley Road from river working west.
·         Nicor has demobilized and will continue Phase II of the gas main and service replacement along Longvalley Road once the storm sewer work is completed.

Work Anticipated to be completed This week, August 29th to September 2nd
·         Continue with storm sewer installation along Longvalley Road
·         General Site clean-up prior to Labor Day Weekend.

The contractor has started the final phase of the underground utility improvements along Longvalley Road, storm sewer installation. The contractor is replacing the existing storm sewer piping with larger piping to the outfall at the river. Due to the size and location of the new storm sewer, travelling along Longvalley Road has become increasingly more difficult. The Village and contractor are committed to doing everything possible to minimize these delays, but your patience and understanding is definitely appreciated. Depending on work progress and weather conditions, the storm sewer main line installation are anticipated to take another 2 to 3 weeks to complete.

Monday, August 22, 2016

Water Improvements Nearly Complete, Storm Sewer Improvements to Begin on Longvalley Road

Work Completed Last Week, August 15th to August 19th
·         Performed testing and received required approvals to place the remaining portion of the newly installed water main along Longvalley Road into service.
·         Continued water service replacements along Longvalley Road.
·         Made connections to the existing water main at intersections of Crabtree Lane and Rio Vista Road.
·         Nicor Gas completed Phase I of the gas main and service replacements along North Branch Road and Longvalley Road from Country Lane to North Branch Road.

Work Anticipated to be completed This week, August 22nd to 26th  
·         Complete water service replacements along Longvalley Road between Country Lane and North Branch Road
·         Complete connections between the existing water main and the new water main at North Branch Road and Country Lane
·         Begin storm sewer installation along Longvalley Road from river working west.
·         Nicor has demobilized and will continue Phase II of the gas main and service replacement along Longvalley Road once the storm sewer work is completed.

The contractor will complete the water service replacements along Longvalley Road between Country Lane and North Branch Road this week. Water services will be replaced from the new water main to the existing valve and box located in front of each home. During the water service replacement, water to individual homes will be shut-off for approximately 2-3 hours while the transition from the old service to the new service is made. The contractor will notify each resident individually regarding the approximate time and day of the water shut-off prior to turning off the water.

The contractor will also make connections between the existing water main and the newly installed water main at Country Lane and North Branch Road. As with last week, during these connections, the existing and new water main will be need to shut-down. Residents affected by the shut-down are notified the day prior to the shut-down occurring.

A majority of the water system improvements along Longvalley Road will be completed near the middle of the week. The contractor will begin installing the new storm sewer starting at the river and working west.  A majority of the project will be receiving new, and larger, storm sewer piping.

Tuesday, August 16, 2016

Mainline Water Main along Longvalley Road Completed. Water Service Replacements On-Going

Work Completed Last Week, August 8th to August 12th  
·         Completed water main installing along Longvalley Road from river to North Branch Road
·         Performed tests and received required approvals to place a portion of the newly installed water main into service.
·         Began water service replacements along Longvalley Road starting at river and working west.
·         Nicor Gas continued to replace the existing gas main and services along North Branch Road and Longvalley Road.

Work Anticipated to be completed This week, August 15th to 19th
·         Continue to perform testing and receive necessary approvals prior to placing sections of the newly installed water main into service
·         Continue water service replacements along Longvalley Road at east end near river and work west to North Branch Road
·         Nicor gas is anticipating have the 1st Phase of gas main and service replacements, including house switch-overs, completed by the end of the week.

The contractor will continue water service replacements along Longvalley Road starting at the east end near the river and working west towards North Branch Road. Water services will be replaced from the new water main to the existing valve and box located in front of each home. During the water service replacement, water to individual homes will be shut-off for approximately 2-3 hours while the transition from the old service to the new service is made. The contractor will notify each resident individually regarding the approximate time and day of the water shut-off prior to turning off the water.

Monday, August 1, 2016

Water Main on Longvalley Road Continues

Work Completed Last Week, July 25th to July 29th  
·         Started water main installation along Longvalley Road at east end near river and worked west
·         Nicor Gas continued to replace the existing gas main and services along North Branch Road.

Work Anticipated to be completed This week, August 1st to August 5th  
·         Continue water main installation along Longvalley Road towards North Branch Road
·         Nicor Gas to begin work along Longvalley Road replacing the gas main and services in the area.

The contractor will continue with water main installation along Longvalley Road this week, with hopes of installing on the water main to North Branch Road by the end of the week. During water main installation, the contractor will be excavating along the entire length of the roadway in lieu of across the roadway. This will pose additional challenges in traveling along the roadway due to the construction equipment on-site and excavations on the side of the road. Also, those residents that live adjacent to where the working is occurring during the day, access to your driveway will be temporarily restricted as the excavation occurs in front of your driveway. Residents affected by temporary driveway closures will be notified by knocking on your doors and asking to move any vehicles from the driveway or garage prior to excavation occurring. We will do everything possible to limit the travel delays along Longvalley road, but please use care and allow a little extra time. The excavations will be filled at the end of each day, so access to all driveways and the roadway will be restored.

Due to the construction, an existing ComEd electrical line was hit causing a power-outage in the area. The incident is still under investigation regarding the reasons for the electrical line being hit. The good news is no injuries occurred on-site. We apologize for any inconvenience this interruption in electrical service caused.

Thanks again for all your patience and understanding as you live within a construction area.

Monday, July 25, 2016

Water Main on Longvalley Road to Begin

Work Completed Last Week, July 18th to July 22nd 
·         Completed sanitary sewer service replacements along Longvalley Road
·         Completed sanitary sewer pipe repairs as required along Longvalley Road
·         Completed sanitary sewer manhole replacements along Longvalley Road
·         Nicor Gas continued to replace the existing gas main and services along North Branch Road.

 Work Anticipated to be completed Next week, July 25th to July 29th 
·         Start water main installation along Longvalley Road starting at the east end near the river and working west to Rollwind Road
·         Nicor Gas continues to work along North Branch Road replacing the gas main and services in the area.

The contractor has completed a majority of the sanitary sewer system improvements and service replacements along Longvalley Road.  The contractor will begin installing the new 8-inch water main along Longvalley starting on the east end near the river and working west to Rollwind Road. In order to make a connection between the existing water main near the river and the new water main, the water main will need to be shut-down. The Village Water Department will provide notice to those residents affected by the shut-down the day prior to the work occurring.  Currently, the water main shut down is scheduled for Monday, July 25th. Resident affected will be notified on Friday, July 22nd.

As the water main construction begins, the contractor will be excavating along the entire length of the roadway in lieu of across the roadway. This will pose additional challenges in traveling along the roadway due to the construction equipment on-site and excavations on the side of the road. Also, those residents that live adjacent to where the working is occurring during the day, access to your driveway will be temporarily restricted as the excavation occurs in front of your driveway. Residents affected by temporary driveway closures will be notified by knocking on your doors and asking to move any vehicles from the driveway or garage prior to excavation occurring. We will do everything possible to limit the travel delays along Longvalley road, but please use care and allow a little extra time. The excavations will be filled at the end of each day, so access to all driveways and the roadway will be restored.

Thanks again for all your patience as the water main work begins with the inconveniences of increased travel delays and disruptions to your water service.

Friday, July 15, 2016

Sanitary Sewer Improvements Continue

Work Completed Last Week, July 11th to July 15th
·         Continued with sanitary sewer service replacements along Longvalley Road

Work Anticipated to be completed Next week, July 18th to July 22nd
·         Continue with sanitary sewer service replacements along Longvalley Road
·         Perform sanitary sewer pipe repairs as required.
·         Perform sanitary sewer manhole replacements

The contractor will continue with sanitary sewer service replacements, manhole replacements, and mainline repairs for the upcoming week.

Nicor Gas will begin gas main and service replacements next week along North Branch Road.

Thanks again for all your patience and understanding during the construction project.