Completed sanitary sewer service replacements
along Longvalley Road
·
Completed sanitary sewer pipe repairs as
required along Longvalley Road
·
Completed sanitary sewer manhole replacements
along Longvalley Road
·
Nicor Gas continued to replace the existing gas
main and services along North Branch Road.
·
Start water main installation along Longvalley
Road starting at the east end near the river and working west to Rollwind Road
·
Nicor Gas continues to work along North Branch
Road replacing the gas main and services in the area.
The contractor has completed
a majority of the sanitary sewer system improvements and service replacements
along Longvalley Road. The contractor will begin installing the new
8-inch water main along Longvalley starting on the east end near the river and
working west to Rollwind Road. In order to make a connection between the
existing water main near the river and the new water main, the water main will
need to be shut-down. The Village Water Department will provide notice to those
residents affected by the shut-down the day prior to the work occurring.
Currently, the water main shut down is scheduled for Monday, July 25th.
Resident affected will be notified on Friday, July 22nd.
As the water main
construction begins, the contractor will be excavating along the entire length
of the roadway in lieu of across the roadway. This will pose additional
challenges in traveling along the roadway due to the construction equipment
on-site and excavations on the side of the road. Also, those residents that
live adjacent to where the working is occurring during the day, access to your
driveway will be temporarily restricted as the excavation occurs in front of
your driveway. Residents affected by temporary driveway closures will be
notified by knocking on your doors and asking to move any vehicles from the
driveway or garage prior to excavation occurring. We will do everything possible
to limit the travel delays along Longvalley road, but please use care and allow
a little extra time. The excavations will be filled at the end of each day, so
access to all driveways and the roadway will be restored.
Thanks again for all your
patience as the water main work begins with the inconveniences of increased
travel delays and disruptions to your water service.