Water main installation along North Branch Road
completed
·
Performed necessary testing and received required
approvals to place new water main into service along North Branch Road
·
Replaced water services along North Branch Road
from Country Lane to Central Parkway
·
Made connection between new water main and
existing water main at intersection of North Branch Road and Central Parkway
·
Roadway excavation, grading, and base course
installation along Longvalley Road
·
Installed storm sewer overflow at east end of
Longvalley Road
·
Installed concrete curb & gutter on east end
of Longvalley Road
·
Storm sewer installation started along North
Branch Road
·
Nicor gas main and service replacements along
Longvalley Road and North Branch Road nearly completed
Work Anticipated to be completed This week, October 17th
to 21st
·
Pave first layer of asphalt pavement along
Longvalley Road from river to North Branch Road.
·
Water service replacements along North Branch
Road from Longvalley Road to Country Lane
Water service replacements along North Branch Road will
begin next week. Water services will be replaced from the new water main to the
existing valve and box located in front of each home. During the water service
replacement, water to individual homes will be shut-off for approximately 2-3
hours while the transition from the old service to the new service is made. The
contractor will notify each resident individually regarding the approximate
time and day of the water shut-off prior to turning off the water.
It is anticipated water service replacements along North
Branch Road will take the majority of next week and may not be completed until
early the week of October 24th. Once the water service replacement
are completed, the contractor will continue with the storm sewer improvements
along North Branch Road.
The contractor started the roadway improvements along
Longvalley Road by removing the existing materials to the depth required for
the new asphalt pavement along with grading and installing aggregate base
course. It is anticipated the first layer of asphalt pavement will be installed
next week. This will be a significant project milestone for those residents
along Longvalley Road by providing a smooth driving surface and greatly
reducing the amount of dust created.
Thanks again for all your patience and understanding.