Friday, July 15, 2016

Sanitary Sewer Improvements Continue

Work Completed Last Week, July 11th to July 15th
·         Continued with sanitary sewer service replacements along Longvalley Road

Work Anticipated to be completed Next week, July 18th to July 22nd
·         Continue with sanitary sewer service replacements along Longvalley Road
·         Perform sanitary sewer pipe repairs as required.
·         Perform sanitary sewer manhole replacements

The contractor will continue with sanitary sewer service replacements, manhole replacements, and mainline repairs for the upcoming week.

Nicor Gas will begin gas main and service replacements next week along North Branch Road.

Thanks again for all your patience and understanding during the construction project.