Completed installation of mainline storm sewer
along Longvalley Road
·
Continued with minor repairs of existing storm
sewer along Longvalley Road
·
Replaced storm sewer services along Longvalley
Road as needed or planned
·
Completed final water main connections along
Longvalley Road
o
Water main improvements along Longvalley Road
are completed.
·
Started abandonment of fire hydrants and valves
on old water main system
·
Grinding-in-place of existing roadway along
North Branch Road
Work Anticipated to be completed This week, September 19th
to 23rd
·
Complete minor repairs in existing storm sewer
along Longvalley Road
·
Complete storm sewer service replacements along
Longvalley Road as planned
·
Begin sanitary sewer service replacements on the
west side of North Branch Road
·
Nicor Gas to begin gas main and service
replacements along Longvalley Road from Country Lane east to river.
The contractor has continued to work on the storm sewer
improvements and repairs to the existing storm sewer system along Longvalley
Road. It is anticipated all underground utility improvements will be completed
on Longvalley Road near the middle of this week.
The contractor will move to North Branch Road to begin
underground utility improvements this week. The contractor will begin with
replacing those sanitary sewer services on the west side of the street. The
sanitary sewer services on the west side of the street go under the roadway;
therefore, are being replaced as part of this project prior to the roadway
improvements. The sanitary sewer services on the east side of the street will
not be replaced as part of this project since they do not go under the roadway.
Nicor will also begin mobilizing back to the project site to
begin gas main and service replacement along Longvalley Road from Country Lane
to the river.