Water service replacements along North Branch
Road
·
Final water main connection at North Branch Road
and Country Lane
·
Storm sewer installation along North Branch Road
·
Storm sewer replacement between 342 & 348
North Branch Road
·
Paved first layer of asphalt pavement along
Longvalley Road from river to North Branch Road
·
Adjusting manholes to grade along Longvalley
Road
·
Driveway replacements along Longvalley Road
·
Rough grading and topsoil installation in
preparation for sod along Longvalley Road
·
Fine grading topsoil and sod installation along
Longvalley Road
·
Nicor gas main and service replacements along
Longvalley Road and North Branch Road is now completed.
Work Anticipated to be completed This week, October 31st
to November 4th
·
Complete storm sewer installation along North
Branch Road
·
Begin roadway improvements including removing
the existing roadway, grading, and installing new aggregate base course in
preparation for asphalt pavement.
·
Continue with fine grading topsoil and sod
installation along Longvalley Road
The restoration work along Longvalley Road is on-going and
will be nearly completed by the end of next week. The contractor will leave
approximately 2 feet of sod to be installed following the roadway surface
paving. The reason for leaving this area along the edge of pavement is so the
contractor can match the new asphalt surface once it is paved.
Storm sewer installation along North Branch Road is on-going
and is expected to be completed by the end of the week. Once the storm sewer is
completed, all underground utility work will be completed and the roadway
improvements will begin.
As the weather gets colder, we are closing in on the end of
the construction season. The long-range schedule to complete the project this
year includes:
North Branch Road:
·
Week of November 7th – Complete
roadway excavation and preparation work for asphalt pavement
·
Week of November 14th – Pave first
layer of asphalt pavement. Begin driveway restorations.
·
Week of November 21st (Prior to
Thanksgiving) – Adjust Manholes to grade. Pave surface layer of asphalt.
·
Week of November 28th – Sod
Restoration.
Longvalley Road
·
Week of November 7th – Clean site and
demobilize from construction staging area
·
Week of November 14th – Pave final
surface layer of asphalt pavement
·
Week of November 21st – Complete sod
restoration.
Thanks again for all your patience and understanding
throughout the construction process. A significant amount of work has been
completed the past several weeks and will continue for the next several weeks
to get the project completed prior to the end of the construction season.