Underground utility work along Longvalley Road completed.
·
Sanitary sewer service replacements on west side of North Branch Road
completed
·
Sanitary sewer manhole replacements along North Branch Road completed
·
Water main installation started along North Branch Road
·
Storm sewer installation started along North Branch Road
·
Nicor Gas began gas main and service replacements along Longvalley Road
Work Anticipated to be completed This week, October 3rd
to 7th
·
Complete water main installation along North Branch Road
·
Continue with storm sewer installation along North Branch Road
·
Perform required testing on newly installed water main prior to placing
into service and beginning water service replacements along North Branch Road
·
Nicor gas to continue with gas main and service replacements along
Longvalley Road
The underground utility work along Longvalley Road is now
completed; therefore, Nicor Gas re-mobilized to the site to begin the gas main
and service replacements. It is anticipated Nicor will be completed with a
majority of their work by the end of the week of October 3rd.
Once the gas main and service replacements are completed, Nicor will be
contacting each resident individually to schedule a time to switch from the old
gas service to the new gas service. Please coordinate with Nicor to allow for
this transition to occur as quickly as possible.
The contractor has moved on to North Branch Road to begin
underground utility improvements. The sanitary sewer improvements are mostly
completed. The water main and storm sewer installation is on-going. It is anticipated
water service replacements will begin later this week or next week.
Once water service replacements begin along North Branch
Road, water services will be replaced from the new water main to the existing
valve and box located in front of each home. During the water service
replacement, water to individual homes will be shut-off for approximately 2-3
hours while the transition from the old service to the new service is made. The
contractor will notify each resident individually regarding the approximate
time and day of the water shut-off prior to turning off the water.
It is also anticipated the contractor will begin the roadway
improvements along Longvalley Road the week of October 10th.
Thanks again for all your patience and understanding.