Monday, October 31, 2016

Longvalley Restoration On-Going. North Branch Storm Sewer Nearing Completion, Start Roadway Improvements.

Work Completed Last Week, October 24th to 29th  
·         Water service replacements along North Branch Road
·         Final water main connection at North Branch Road and Country Lane
·         Storm sewer installation along North Branch Road
·         Storm sewer replacement between 342 & 348 North Branch Road
·         Paved first layer of asphalt pavement along Longvalley Road from river to North Branch Road
·         Adjusting manholes to grade along Longvalley Road
·         Driveway replacements along Longvalley Road
·         Rough grading and topsoil installation in preparation for sod along Longvalley Road
·         Fine grading topsoil and sod installation along Longvalley Road
·         Nicor gas main and service replacements along Longvalley Road and North Branch Road is now completed.

Work Anticipated to be completed This week, October 31st to  November 4th
·         Complete storm sewer installation along North Branch Road
·         Begin roadway improvements including removing the existing roadway, grading, and installing new aggregate base course in preparation for asphalt pavement.
·         Continue with fine grading topsoil and sod installation along Longvalley Road

The restoration work along Longvalley Road is on-going and will be nearly completed by the end of next week. The contractor will leave approximately 2 feet of sod to be installed following the roadway surface paving. The reason for leaving this area along the edge of pavement is so the contractor can match the new asphalt surface once it is paved.

Storm sewer installation along North Branch Road is on-going and is expected to be completed by the end of the week. Once the storm sewer is completed, all underground utility work will be completed and the roadway improvements will begin.

As the weather gets colder, we are closing in on the end of the construction season. The long-range schedule to complete the project this year includes:

North Branch Road:
·         Week of November 7th – Complete roadway excavation and preparation work for asphalt pavement
·         Week of November 14th – Pave first layer of asphalt pavement. Begin driveway restorations.
·         Week of November 21st (Prior to Thanksgiving) – Adjust Manholes to grade. Pave surface layer of asphalt.
·         Week of November 28th – Sod Restoration. 

Longvalley Road
·         Week of November 7th – Clean site and demobilize from construction staging area
·         Week of November 14th – Pave final surface layer of asphalt pavement
·         Week of November 21st – Complete sod restoration.

Thanks again for all your patience and understanding throughout the construction process. A significant amount of work has been completed the past several weeks and will continue for the next several weeks to get the project completed prior to the end of the construction season. 

Saturday, October 15, 2016

Roadway Paving along Longvalley Road. Water Service Replacements along North Branch Road.

Work Completed Last Week, October 10th to 14th  
·         Water main installation along North Branch Road completed
·         Performed necessary testing and received required approvals to place new water main into service along North Branch Road
·         Replaced water services along North Branch Road from Country Lane to Central Parkway
·         Made connection between new water main and existing water main at intersection of North Branch Road and Central Parkway
·         Roadway excavation, grading, and base course installation along Longvalley Road
·         Installed storm sewer overflow at east end of Longvalley Road
·         Installed concrete curb & gutter on east end of Longvalley Road
·         Storm sewer installation started along North Branch Road
·         Nicor gas main and service replacements along Longvalley Road and North Branch Road nearly completed

Work Anticipated to be completed This week, October 17th to 21st  
·         Pave first layer of asphalt pavement along Longvalley Road from river to North Branch Road.
·         Water service replacements along North Branch Road from Longvalley Road to Country Lane

Water service replacements along North Branch Road will begin next week. Water services will be replaced from the new water main to the existing valve and box located in front of each home. During the water service replacement, water to individual homes will be shut-off for approximately 2-3 hours while the transition from the old service to the new service is made. The contractor will notify each resident individually regarding the approximate time and day of the water shut-off prior to turning off the water.

It is anticipated water service replacements along North Branch Road will take the majority of next week and may not be completed until early the week of October 24th. Once the water service replacement are completed, the contractor will continue with the storm sewer improvements along North Branch Road.

The contractor started the roadway improvements along Longvalley Road by removing the existing materials to the depth required for the new asphalt pavement along with grading and installing aggregate base course. It is anticipated the first layer of asphalt pavement will be installed next week. This will be a significant project milestone for those residents along Longvalley Road by providing a smooth driving surface and greatly reducing the amount of dust created.

Thanks again for all your patience and understanding.

Monday, October 3, 2016

Underground Utility Improvements Continue along North Branch Road

Work Completed Last Week, September 26th to 30th
·         Underground utility work along Longvalley Road completed.
·         Sanitary sewer service replacements on west side of North Branch Road completed
·         Sanitary sewer manhole replacements along North Branch Road completed
·         Water main installation started along North Branch Road
·         Storm sewer installation started along North Branch Road
·         Nicor Gas began gas main and service replacements along Longvalley Road

Work Anticipated to be completed This week, October 3rd to 7th  
·         Complete water main installation along North Branch Road
·         Continue with storm sewer installation along North Branch Road
·         Perform required testing on newly installed water main prior to placing into service and beginning water service replacements along North Branch Road
·         Nicor gas to continue with gas main and service replacements along Longvalley Road

The underground utility work along Longvalley Road is now completed; therefore, Nicor Gas re-mobilized to the site to begin the gas main and service replacements. It is anticipated Nicor will be completed with a majority of their work by the end of the week of October 3rd.  Once the gas main and service replacements are completed, Nicor will be contacting each resident individually to schedule a time to switch from the old gas service to the new gas service. Please coordinate with Nicor to allow for this transition to occur as quickly as possible.

The contractor has moved on to North Branch Road to begin underground utility improvements. The sanitary sewer improvements are mostly completed. The water main and storm sewer installation is on-going. It is anticipated water service replacements will begin later this week or next week.

Once water service replacements begin along North Branch Road, water services will be replaced from the new water main to the existing valve and box located in front of each home. During the water service replacement, water to individual homes will be shut-off for approximately 2-3 hours while the transition from the old service to the new service is made. The contractor will notify each resident individually regarding the approximate time and day of the water shut-off prior to turning off the water.

It is also anticipated the contractor will begin the roadway improvements along Longvalley Road the week of October 10th.

Thanks again for all your patience and understanding.

Monday, September 19, 2016

Underground Improvements on Longvalley Road Nearly Complete. Work on North Branch Road to Begin

Work Completed Last Week, September 12th to 16th   
·         Completed installation of mainline storm sewer along Longvalley Road
·         Continued with minor repairs of existing storm sewer along Longvalley Road
·         Replaced storm sewer services along Longvalley Road as needed or planned
·         Completed final water main connections along Longvalley Road
o   Water main improvements along Longvalley Road are completed.
·         Started abandonment of fire hydrants and valves on old water main system
·         Grinding-in-place of existing roadway along North Branch Road

Work Anticipated to be completed This week, September 19th to 23rd   
·         Complete minor repairs in existing storm sewer along Longvalley Road
·         Complete storm sewer service replacements along Longvalley Road as planned
·         Begin sanitary sewer service replacements on the west side of North Branch Road
·         Nicor Gas to begin gas main and service replacements along Longvalley Road from Country Lane east to river.

The contractor has continued to work on the storm sewer improvements and repairs to the existing storm sewer system along Longvalley Road. It is anticipated all underground utility improvements will be completed on Longvalley Road near the middle of this week.

The contractor will move to North Branch Road to begin underground utility improvements this week. The contractor will begin with replacing those sanitary sewer services on the west side of the street. The sanitary sewer services on the west side of the street go under the roadway; therefore, are being replaced as part of this project prior to the roadway improvements. The sanitary sewer services on the east side of the street will not be replaced as part of this project since they do not go under the roadway.

Nicor will also begin mobilizing back to the project site to begin gas main and service replacement along Longvalley Road from Country Lane to the river.

Thursday, September 8, 2016

Closure of Longvalley Road & Country Lane Extended to Friday, September 9th

Due to work not progressing as anticipated, the closure of the intersection at Longvalley Road and Country Lane will be extended through Friday, September 9th.

It is anticipated the work within the intersection will be completed by the end of the day on Friday.

Please use an alternate route around the intersection.

Thanks again for your patience.

Tuesday, September 6, 2016

Intersection of Longvalley Road and Country Lane Closed on Thursday, September 8th

In order to complete the storm sewer improvements within the intersection of Longvalley Road and Country Lane, the intersection will be closed to traffic in all directions on Thursday, September 8th from 7:00 AM to 5:00 PM.

The school districts and bus companies have been notified of this closure.

Please use an alternate route through the neighborhood and plan accordingly to avoid delays.

Storm Sewer Installation Continues along Longvalley Road

Work Completed Last Week, August 29th to September 2nd  
·         Continued with storm sewer installation along Longvalley Road.
·         Storm sewer main line completed from river to Rollwind Road
·         Site clean-up prior to Labor Day Weekend.

Work Anticipated to be completed This week, September 5th to 9th.  
·         Continue with storm sewer installation along Longvalley Road from Rollwind Road west towards North Branch Road
·         Storm sewer installation within intersection of Longvalley Road and Country Lane.
·         Complete final water main connections at intersection of Longvalley Road and Rollwind Road

The contractor has continued with the storm sewer installation along Longvalley Road, working within several intersections last week and scheduled again for this week. Last week, work within the intersections of Crabtree Lane / Rio Vista Lane and Rollwind Road was completed.  This week, it is anticipated work will continue within the intersections of Rollwind Road and Country Lane.

Thank you for all your patience as getting through these intersections and around the neighborhood has been challenging. The Village of Glenview has been in contact with the school districts in the area to update them on the construction progress and schedule to ensure the buses are able to navigate through the construction area.

It is anticipated the storm sewer improvements along Longvalley Road will be completed within the next 2 weeks. Once the storm sewer is completed, the contractor will begin the underground utility improvements along North Branch Road.